Each question is worth 1.7857 points.
PERT Network Diagram 1 illustrates ten interrelated activities that comprise a certain project.
PERT Network Diagram 1
The information presented in Table 1 represents the optimistic activity time (a), most probable activity time (m), and pessimistic activity time (b) in weeks for each activity associated with the project.
Table 1
Estimated Completion Time (Weeks) | |||
Activity | Optimistic (a) | Most Probable (m) | Pessimistic (b) |
A | 1 | 3 | 5 |
B | 1 | 2 | 3 |
C | 2 | 4 | 6 |
D | 1 | 2 | 3 |
E | 2 | 4 | 6 |
F | 1 | 3 | 5 |
G | 2 | 4 | 6 |
H | 1 | 3 | 5 |
I | 2 | 4 | 6 |
J | 1 | 4 | 7 |